Construction Act payment timetable
Payment timetable
Under the contract, payment falls due 14 days after the valuation period ended on Friday, 4 December 2026.
Payment due date | Friday, 18 December 2026 |
Payment notice due by | Wednesday, 23 December 2026 |
Final date for payment | Monday, 8 February 2027 |
Pay less notice due by | Monday, 1 February 2027 |
The payment notice given on Wednesday, 6 January 2027 came after the deadline of Wednesday, 23 December 2026, so it does not count as one.
No payment notice was given by Wednesday, 23 December 2026. The payee's notice of Thursday, 14 January 2027 stands as the notified sum, and moves the final date for payment back 18 days, from Thursday, 21 January 2027 to Monday, 8 February 2027.
Days are counted under section 116 of the Housing Grants, Construction and Regeneration Act 1996: Christmas Day, Good Friday and bank holidays in Scotland are not counted. Weekends are.