Stage payment schedule

Stage payments

The contract sum of £48,752,500.33 is paid in 8 stages, after a deposit of £4,875,250.03.

Stage

Status

Amount

VAT

Tax point

Deposit

Received 16 Feb 2026

£4,875,250.03

£975,050.01

16 Feb 2026

Site establishment, enabling works and temporary services (£3,500,000.00 less £3,500,000.00 of the deposit)

Paid 27 Mar 2026

£0.00

£0.00

6 Mar 2026

Substructure, piling and ground-floor slab complete (£6,094,062.54 less £1,375,250.03 of the deposit)

Paid 13 May 2026

£4,718,812.51

£943,762.50

13 May 2026

Frame, upper floors and roof structure topped out

Invoiced 7 Aug 2026

£8,531,687.55

£1,706,337.51

7 Aug 2026

Building envelope weathertight, including curtain walling

Reached 19 Oct 2026

£7,312,875.04

Not yet due

Not yet

Mechanical, electrical and plumbing first fix complete

Not yet reached

£7,312,875.04

Not yet due

Not yet

Internal finishes, second fix and commissioning

Not yet reached

£6,094,062.54

Not yet due

Not yet

Practical completion and handover of the building

Not yet reached

£4,875,250.03

Not yet due

Not yet

Making good defects at the end of the rectification period

Not yet reached

£5,031,687.59

Not yet due

Not yet

Paid

£9,594,062.54

£1,918,812.51

Invoiced, not yet paid

£8,531,687.55

£1,706,337.51

Not yet invoiced

£30,626,750.24

Not yet due

Contract sum

£48,752,500.33

VAT on each stage is due at its tax point: the date it is invoiced or paid, whichever comes first. Reaching a stage is not a tax point, so a stage that is reached but not yet invoiced has no VAT due. VAT on the deposit was due when it was received, so each stage's VAT is worked on what is left of it after the deposit.